Question–answer pairs derived from MRT Corporation (Malaysia) annual, progress, and financial reports (2012–2021).
Each record includes a question, concise answer, supporting context, and a fixed ticker MRTCMY.
📦 Files
| File | Description |
|---|---|
train.jsonl |
Full dataset in JSON Lines format |
README.md |
This dataset card |
🔧 Schema
Each line in train.jsonl is a JSON object:
{"question":"...","answer":"...","context":"...","ticker":"MRTCMY"}
| Field | Type | Description |
|---|---|---|
question |
string | Financial/project question |
answer |
string | Concise factual answer |
context |
string | Source-backed supporting excerpt |
ticker |
string | Always "MRTCMY" |
📊 Split
| Split | Records |
|---|---|
| train | 242 |
📈 Basic Statistics
| Metric | Question | Answer | Context |
|---|---|---|---|
| Avg. length (chars) | 83.2 | 46.5 | 107.8 |
| Max length (chars) | 125 | 195 | 304 |
Note: Lengths are character counts for a quick sense of prompt/label sizes.
👀 Preview (first 12 rows)
| question | answer | ticker |
|---|---|---|
| What is the total length of the MRT Sungai Buloh–Kajang (SBK) Line? | 51 km. | MRTCMY |
| How many stations are on the SBK Line, and how much of the line is elevated vers… | 31 stations; 41.5 km elevated and 9.5 km underground. | MRTCMY |
| What is the estimated daily ridership for the SBK Line? | Over 400,000 passengers per day. | MRTCMY |
| What is the estimated journey time from Kota Damansara to Bukit Bintang on the S… | About 30 minutes. | MRTCMY |
| When were Phase One and Phase Two of the SBK Line expected to become operational… | Phase One (Sungai Buloh to Semantan) by end-2016; Phase Two … | MRTCMY |
| Who was awarded the underground works package and what was its value? | MMC-Gamuda KVMRT (T) Sdn Bhd; RM8.28 billion. | MRTCMY |
| Which company supplied the electric trains for the SBK Line? | Siemens Malaysia Sdn Bhd. | MRTCMY |
| Who was responsible for the signalling and train control system? | Bombardier (M) Sdn Bhd. | MRTCMY |
| How much compensation had been paid for land acquisition as of September 2012? | RM1,235,748,070.82. | MRTCMY |
| What percentage and value of main work packages were awarded to Bumiputera compa… | 45% of the total value, amounting to RM8.8247 billion. | MRTCMY |
| What was MRT Corp’s net loss for the financial year ended 30 September 2012? | RM7.233 million. | MRTCMY |
| What was the amount of property, plant and equipment as at FY2012? | RM1,360.953 million. | MRTCMY |
🔽 Loading with 🤗 Datasets
from datasets import load_dataset
ds = load_dataset("json", data_files="train.jsonl", split="train")
print(ds[0])
📚 Sources
Public MRT Corp (Malaysia) Annual Progress & Financial Reports, 2012–2021.
📜 License
Derived from public MRT Corp reports. Redistribution for research/education. Check local rights for commercial use.
🙌 Citation
@dataset{mrtcorp_financial_qa_2025,
title = {MRTCMY Financial QA Dataset},
author = {Epan},
year = {2025},
url = {https://huggingface.co/datasets/<your-username>/MRTCMY-Financial-QA}
}
- Downloads last month
- 3